• September-2023Chairman Sukh Chayn Residence participated in a tree plantation activity

    • CHAIRMAN Sukh Chayn Residence personally plants 60 trees for the environment surrounding the main access road
    • Access road and road sleeve works initiated
    • Waterproofing for ground floor garden base initiated
    • Guard house work completed
    • Smart Building Management System ready for deployment
    • Swimming pool area finishing works in progress
    • Airconditioning outers installation in progress
    • Airconditioning indoor cassette installation in progress
    • Kitchen fixture & fitting works halted due to delay in equipment resumes
    • Bus Bar System installation
    • Meter installation by IESCO
  • August-2023Progress of Finishing Works

    • OTIS elevators arrive on site and installation works initiated
    • Transformers arrive on site and installation work initiated
    • Water pump and Firefighting pumps received on site and installation work initiated
    • Reception area glass ceiling Installation completed
    • Reception Area finishing works in progress
    • CAFÉ’ Area Finishing works completed
    • Community Hall Finishing works completed
    • Swimming pool water-line works completed
    • Gym area finishing works nearing completion
    • Main drop-off area civil works in active progress
    • Access road to main entrance development work in progress
  • May-2023Government lifts ban on imports and supply resumes

    • Apartment balcony railings installed
    • Apartment balcony parapet glass 6mm by 6mm tempered laminated glass for extra support installed
    • Alucobond Fire rated Aluminum composite Panel reveals itself on the west tower
    • Corridor tyle works completed
    • ALLUCOBOND installation over swimming pool area completed
  • April-2023Mr. Saleh Azeem is honored as the youngest recipient of Tamgha-e-Imtiaz

    CEO Sukh Chayn Residence Mr. Saleh Azeem is honored as the youngest recipient of Tamgha-e-Imtiaz (medal of excellence) for being at the forefront of establishing innovative and sustainable projects for the betterment of the construction industry of Pakistan and in recognition for his public services to the flood affectees by building 100 homes, an infirmary and a school within 30 days. (THE NATION)
  • February-2023Prolonged import ban and unexcepted port closure further delays

    • Apartment window installation completed
    • Ceiling works of Apartments completed
    • Apartment base coat paint works completed
    • Apartment doors & fittings completed
    • Installation of kitchen fixtures & fittings suspended pending import
    • Swimming Pool works initiated regardless of delay in ACP supply
    • Reception & Main Lobby area finishing works initiated pending completion of ALUCOBOND installation above
    • Gym Area Finishing works Initiated
    • Community Area finishing works initiated
    • CAFE’ area finishing works initiated
  • October-2022Ban on import persists, delaying the supply of vital equipment & machinery

    Government Order
    • Apartment window installation nearing completion
    • Ceiling work of Apartments nearing completion
    • Apartment base coat paint works nearing completion
    • Apartment doors & fittings installation in progress
    • Installation of kitchen fixtures & fittings suspended due to delay in supply for complimenting works
    • Installation of washroom and shower fixtures & completed
    • Alucobond Fire rated Aluminum composite Panel Installation in progress
  • June-2022Progress of Finishing Works

    • Plumbing Line works completed
    • Firefighting line works completed
    • Air conditioning duct works completed
    • Apartment window installation in progress
    • Apartment window installation in progress
    • Apartment Door Installation initiated
    • Installation of kitchen fixtures & fittings initiated
    • Installation of washroom and shower fixtures & fittings initiated
    • Cabinetry works initiated
    • Smart Building Management System development initiated
    • Government of Pakistan Ministry of Commerce under S.R.O.598(I)/2022, imposes ban on imports May 2022 effecting supply of import of vital equipment for Sukh Chayn Residence
  • February-2022Progress of Finishing Works

    Basement 1, 2 & 3 finishing works (75% complete)

    • Main Entrance (Under Construction)
    • EPS wall partitions construction completed (Ground to 11th Floor)
    • Electrical works including data networks (In active progress: As high as the 5th & 6th Floor)
    • Plumbing Line works (In active progress: As high as the 5th Floor)
    • Water Line works (In active progress: As high as the 5th Floor)
    • Fire Fighting & Fire Sprinkler Line work in active progress
    • Perimeter wall & Entry/Exit gates (under construction)
  • October-2021Progress of Finishing Works

    · EPS Wall Partitioning Works In Final Stages · Parking Basement Finishing Work In Progress · Finishing works In Active Progress: o Fire Fighting Lines o Water Lines o Plumbing Lines o Electrical Lines o Data Network Lines
  • August-2021Grey Structure Construction Completed

  • June-2021World Renowned Samsung Selected For Air Solutions

  • May-2021Internal EPS Wall Partitioning Work Active

  • April-2021Twelfth Floor Construction Complete

  • February-2021Tenth Floor Construction Complete

  • January-2021Finishing Works Initiated

    o Fire Fighting Lines o Water Lines o Plumbing Lines o Electrical Lines o Data Network Lines
  • December-2020Ninth Floor Construction Complete

  • October-2020Eighth Floor Construction Complete

  • September-2020Seventh Floor Construction Complete

  • August-2020Sixth Floor Construction Complete

  • July-2020Fifth Floor Construction Complete

  • June-2020Fourth Floor Construction Complete

  • May-2020Third Floor Construction Complete

  • March-2020Second Floor Construction Complete

  • January-2020First Floor Construction Complete

  • December-2019Ground Floor Construction Complete

  • August-2019First Basement Construction

  • May-2019Second Basement Construction

  • January-2019Third Basement Construction

  • February-2019Raft Foundation Completed

    Major milestone completed with the completion of the final concrete pour for the Raft Foundation. About a quarter of all the concrete for the building sits in the Raft Foundation.
  • 1-January-2019Sukh Chayn Residence Launches New 1 & 2 Bedroom Apartments

  • 02-December-2018Water Proofing & Raft Foundation Construction

  • 01-December-2018Excavation Completed

  • 01-May-2018Ground Breaking & Excavation

  • 30-April-2018Sukh Chayn Residence Launched

  • 6-April-2018CDA Issues NOC

    CDA Approves Building Plan for Sukh Chayn Residence

  • June-2017Design Contract Awarded To ASA


  • 5-May-2017Certificate of Possession

    Full payment made to CDA and possession signed over to Sukh Chayn Valley Pvt. Ltd.

  • March-2017Vision of the Building shared with Top Architects

  • 12-Dec-2016CDA Auction

    Plot #6, 10th Avenue, F-10/4 CDA Press Release
    Sukh Chayn Pvt. Ltd. wins bid.